Filters
Question type

Study Flashcards

A direct labour price standard is frequently called the direct labour efficiency standard.

A) True
B) False

Correct Answer

verifed

verified

Labour efficiency is measured by the


A) materials quantity variance.
B) total labour variance.
C) labour quantity variance.
D) labour rate variance.

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

Use the following information for questions Bridgeware Company has a materials price standard of $2.50 per kilogram.Four thousand kilograms of materials were purchased at $2.40 a kilogram.The actual quantity of materials used was 3,500 kilograms, although the standard quantity allowed for the output was 3,400 kilograms. -Bridgeware Company's total materials variance is


A) $1,100 U.
B) $1,500 U.
C) $1,250 U.
D) $100 F.

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

If actual costs are less than standard costs, the variance is favourable.

A) True
B) False

Correct Answer

verifed

verified

Standard cost is the industry average cost for a particular item.

A) True
B) False

Correct Answer

verifed

verified

In using variance reports, management looks for


A) total assets invested.
B) significant variances.
C) competitors' costs in comparison to the company's costs.
D) more efficient ways of valuing inventories.

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

Use the following information for questions Bridgeware Company has a materials price standard of $2.50 per kilogram.Four thousand kilograms of materials were purchased at $2.40 a kilogram.The actual quantity of materials used was 3,500 kilograms, although the standard quantity allowed for the output was 3,400 kilograms. -Bridgeware Company's materials price variance is


A) $400 U.
B) $400 F.
C) $350 U.
D) $300 F.

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

A favourable variance


A) is an indication that the company is not operating in an optimal manner.
B) implies a positive result if quality control standards are met.
C) implies a positive result if standards are flexible.
D) means that standards are too loosely specified.

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

The difference between fixed overhead budgeted and overhead applied is the


A) budget variance.
B) spending variance.
C) total overhead variance.
D) volume variance.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Allowance for spoilage is part of the direct


A) materials price standard.
B) materials quantity standard.
C) labour price standard.
D) labour quantity standard.

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

Inventories CANNOT be valued at standard cost in financial statements.

A) True
B) False

Correct Answer

verifed

verified

An unfavourable labour quantity variance may be caused by


A) paying workers higher wages than expected.
B) paying workers a bonus at year-end.
C) worker fatigue or carelessness.
D) higher pay rates mandated by union contracts.

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

Which of the following statements is FALSE?


A) A standard cost is more accurate than a budgeted cost.
B) A standard is a unit amount.
C) In concept, standards and budgets are essentially the same.
D) The standard cost of a product is equivalent to the budgeted cost per unit of product.

E) B) and C)
F) None of the above

Correct Answer

verifed

verified

If standard cost reports emphasize meeting predetermined standards


A) there should be non-financial performance measures available to management to supplement the cost reports.
B) management can control the department properly with standard cost reports.
C) the budget process should be sufficient to support management's performance.
D) all members of the team will be able to properly identify critical variance issues.

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

A standard cost system may be used with


A) job order costing only.
B) process costing only.
C) activity-based costing.
D) either job order or process costing.

E) A) and C)
F) C) and D)

Correct Answer

verifed

verified

The direct labour quantity standard is sometimes called the direct labour


A) volume standard.
B) effectiveness standard.
C) efficiency standard.
D) quality standard.

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

The formula for the materials price variance is


A) (AQ × SP) - (SQ × SP) .
B) (AQ × AP) - (AQ × SP) .
C) (AQ × AP) - (SQ × SP) .
D) (AQ × SP) - (SQ × AP) .

E) All of the above
F) None of the above

Correct Answer

verifed

verified

In designing a balanced scorecard approach for its operations, a company should


A) seek to determine as much detail as possible from its activities.
B) be readily available as a discussion tool between management and shareholders.
C) attempt to link performance measures on a cause and effect basis.
D) eliminate any financial results as these will be dealt with in.

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Which of the following statements about standard costs is FALSE?


A) Properly set standards should promote efficiency.
B) Standard costs facilitate management planning.
C) Standards should not be used in "management by exception."
D) Standard costs can simplify the costing of inventories.

E) A) and B)
F) A) and D)

Correct Answer

verifed

verified

The matrix approach to variance analysis


A) will yield slightly different variances than the formula approach.
B) is more accurate than the formula approach.
C) does not separate the price and quantity variance calculations.
D) provides a convenient structure for determining each variance.

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

Showing 101 - 120 of 130

Related Exams

Show Answer