Filters
Question type

Study Flashcards

A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may cause delivery delays. Which of the following is the BEST risk response strategy?


A) Exploit
B) Enhance
C) Mitigate
D) Communicate

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

Which of the following will identify the MOST potential project risks?


A) Cost-benefit analysis
B) Past project documentation
C) Project budget
D) Benchmarking

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and removal of the vendor. Which of the following documents should the project manager review BEFORE the meeting?


A) Issue log
B) Status report
C) Risk register
D) SOW

E) None of the above
F) All of the above

Correct Answer

verifed

verified

A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility. Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?


A) Email
B) Social media
C) Text messaging
D) Face-to-face

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed. Following are the durations of all tasks: Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed. Following are the durations of all tasks:   Which of the following tasks are on the critical path? A)  A, D, C, G B)  A, B, H, G C)  A, D, E, F D)  A, B, C, G Which of the following tasks are on the critical path?


A) A, D, C, G
B) A, B, H, G
C) A, D, E, F
D) A, B, C, G

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?


A) SLA
B) SOW
C) Change request
D) RFP

E) B) and D)
F) A) and C)

Correct Answer

verifed

verified

A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?


A) Crashing the schedule
B) Prioritizing tasks
C) Determining milestones
D) Developing sprints

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling. Which of the following resources has the authority to authorize this change?


A) Stakeholders
B) Scrum master
C) Project sponsor
D) Project team

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?


A) December 18
B) December 19
C) December 20
D) December 21
E) December 22

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

In which of the following circumstances would faxing be the MOST appropriate communication method?


A) When sending confidential information
B) When resolving complex issues
C) When providing weekly status updates
D) When signatures are required

E) C) and D)
F) None of the above

Correct Answer

verifed

verified

Which of the following risk strategies is represented by the purchase of insurance?


A) Mitigate
B) Accept
C) Transfer
D) Avoid

E) A) and C)
F) All of the above

Correct Answer

verifed

verified

A project scheduler has calculated the project's critical path. Which of the following activities would most likely occur NEXT?


A) Additional task decomposition
B) Resource allocation
C) Dependency determination
D) Task duration identification

E) A) and C)
F) B) and D)

Correct Answer

verifed

verified

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which of the following are critical for the project manager to provide?


A) Cost, schedule, organizational chart, and risks/issues
B) Risks/issues, cost, RACI chart, and action items
C) Schedule, cost, risks/issues, and milestones
D) Action items, organizational chart, schedule, and NDA

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

Which of the following describes a burn rate?


A) The rate at which project documents are disposed.
B) The rate at which project personnel leave the project.
C) The rate at which the project budget is used.
D) The rate at which the timeline increases.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

? new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?


A) Identify and document the risk.
B) Evaluate the impact and justification.
C) Implement the change.
D) Update the documents and plans.

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days. Which of the following characteristics classifies this as a project?


A) Repetitive
B) Ongoing
C) Iterative
D) Temporary

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?


A) Revise the project plan.
B) Update the issue log.
C) Request additional funding.
D) Issue a change request.

E) A) and D)
F) A) and B)

Correct Answer

verifed

verified

Which of the following is the BEST reason to conduct regular risk reviews?


A) Risk reviews ensure stakeholders take action on assigned items.
B) Risk reviews allow for the identification of response strategies.
C) Risk reviews can keep personnel on track with their assigned tasks.
D) Risk reviews must be reported in status updates.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process. Which of the following conflict resolution techniques has the project manager utilized?


A) Smoothing
B) Forcing
C) Compromising
D) Avoiding

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

The supervisor asks an engineer to be a project manager within the department. Of which of the following types of organizational structures is this an example?


A) Projectized
B) Functional
C) Matrix
D) Intermediary

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

Showing 61 - 80 of 540

Related Exams

Show Answer