Given a project schedule with all tasks connected with one-way arrows and task durations. The critical path is _____.​


A) the longest path through the network
B) ​the shortest path through the network
C) neither the longest nor shortest path through the network
D) ​it cannot be determined

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

The deployment of a new system resulted in the reduction of the office staff from seven people to five people. This is an example of a(n)______ _______.​

Correct Answer

verifed

verified

​Since the Agile philosophy embraces change,project scope management is not important for Agile projects.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is NOT one of the external responsibilities of a project manager?​


A) Report project status
B) ​Assess project risks
C) Work with the client
D) ​Identify resource needs

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

Which two of the following are activities belonging to the first core process?​


A) Schedule the work
B) ​Perform risk and feasibility analysis
C) Choose the project manager
D) ​Establish the project environment
E) Evaluate the work processes​
F) Quantify project approval factors

G) A) and E)
H) B) and C)

Correct Answer

verifed

verified

The _______  consists of clients and key manager who review the progress and direct the project.​

Correct Answer

verifed

verified

oversight ...

View Answer

In adaptive,iterative projects there are usually two types of schedules created.​

A) True
B) False

Correct Answer

verifed

verified

Which of the following is NOT one of the activities associated with staffing the project team?​


A) Conducting team-building exercises.
B) ​Developing a resource plan.
C) Organizing work groups.
D) ​Setting up programming rules and guidelines.

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

The organization and direction of other people to achieve a planned result within a predetermined schedule and budget is called what?​


A) Project delivery management
B) ​Project integration management
C) Project human resource management
D) ​Project management

E) All of the above
F) B) and D)

Correct Answer

verifed

verified

List the four activities of the first core process: Identify the problem and obtain approval.​

Correct Answer

verifed

verified

1.Identify the problem
2.Quant...

View Answer

Which of the following is NOT one of the internal responsibilities of a project manager?​


A) Develop the project schedule
B) ​Develop specifications
C) Assign work to team members
D) ​Monitor project milestones

E) A) and D)
F) C) and D)

Correct Answer

verifed

verified

Although most project status can be reported electronically,for most projects a periodic printed status report (such as a newsletter)is still critically important.​

A) True
B) False

Correct Answer

verifed

verified

List four primary areas that are considered in risk and feasibility analysis.​

Correct Answer

verifed

verified

1.Organizational risk and feas...

View Answer

​The present value of $200,000 development costs in year 0 assuming a 10% discount rate is:


A) $180,000
B) $190,000​
C) $200,000
D) ​$210,000

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

A project tracking tool that provides a summary of the status of various project items such as open tasks and expenditures is called a(n)______ ______.​

Correct Answer

verifed

verified

With Agile Time Management scheduling is only done on a micro level and not a macro level.​

A) True
B) False

Correct Answer

verifed

verified

The time from the deployment of a new system until the break-even point is reached is sometimes called the ______.​


A) investment period
B) ​net present value
C) return on investment
D) ​payback period

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

​Which would be the least desirable reason to initiate a new development project?


A) To take advantage of a new sales opportunity
B) ​To solve an internal business problem
C) To respond to a legislative requirement​
D) ​To take advantage of new technology

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

A document to help define the scope of the new system is called a(n)  _____ _____ _____.​

Correct Answer

verifed

verified

system vis...

View Answer

The dollar value of benefits reduced by the dollar value of costs combined together and expressed in current dollars is called the ______ _____ _____.​

Correct Answer

verifed

verified

net presen...