Filters
Question type

Study Flashcards

List and briefly describe the main processes involved in project time management.

Correct Answer

verifed

verified

The main processes involved in project t...

View Answer

A merge occurs when one node precedes mutiple nodes.

A) True
B) False

Correct Answer

verifed

verified

The arrows in a network diagram represent missed milestones in a project.

A) True
B) False

Correct Answer

verifed

verified

In the activity defining process, the project team should review the _____ and activity attributes with project stakeholders before moving on to the next step in project time management.

Correct Answer

verifed

verified

An activity is an element of work that has an expected duration, cost, and resource requirements.

A) True
B) False

Correct Answer

verifed

verified

The technique of fast tracking can result in lengthening the project schedule.

A) True
B) False

Correct Answer

verifed

verified

In a project schedule, the variable that has the least amount of flexibility is _____.

Correct Answer

verifed

verified

The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost is known as _____.


A) dependency
B) crashing
C) critical chain scheduling
D) feeding buffers

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.

A) True
B) False

Correct Answer

verifed

verified

Which of the following types of dependencies are inherent in the nature of work being performed on a project?


A) Mandatory
B) Discretionary
C) External
D) Random

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

The _____ is based on the fact that any complex system at any point in time often has only one aspect or constraint that limits its ability to achieve more of its goal.

Correct Answer

verifed

verified

Theory of ...

View Answer

In project time management, a(n) _____ is an output of controlling the schedule


A) activity duration estimate
B) project management plan update
C) activity attribute
D) milestones list

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

A(n) _____ on a project is a significant event that normally has no duration.


A) milestone
B) activity attribute
C) activity sequence
D) schedule baseline

E) B) and C)
F) None of the above

Correct Answer

verifed

verified

In project time management, the ultimate goal of _____ is to provide a basis for monitoring project progress for the time dimension of the project.


A) defining activities
B) sequencing activities
C) developing a schedule
D) estimating activity resources

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

The ultimate goal of developing a realistic project schedule is to provide a basis for monitoring project progress for the _____ dimension of the project.

Correct Answer

verifed

verified

The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.


A) longest; longest
B) longest; shortest
C) shortest; longest
D) shortest; shortest

E) C) and D)
F) All of the above

Correct Answer

verifed

verified

In project time management, which of the following processes involve analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?


A) Planning schedule management
B) Developing the schedule
C) Controlling the schedule
D) Defining activities

E) B) and C)
F) C) and D)

Correct Answer

verifed

verified

Knowing the amount of float allows project managers to know whether a project schedule is flexible.

A) True
B) False

Correct Answer

verifed

verified

It is important for the activity list and activity attributes to be in agreement with the work breakdown structure.

A) True
B) False

Correct Answer

verifed

verified

In project time management, which of the following processes generate the main outputs of an activity list, activity attributes, and a milestone list?


A) Sequencing activities
B) Defining activities
C) Resource estimating activities
D) Estimating activity durations

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

Showing 61 - 80 of 100

Related Exams

Show Answer