Filters
Question type

Study Flashcards

Answer the following questions using the information below: Roberson Corporation manufactured 30,000 ice chests during September. The variable overhead cost-allocation base is $11.25 per machine-hour. The following variable overhead data pertain to September:  Actual  Budgeted  Production 30,000 units 24,000 units  Machine-hours 15,000 hours 10,800 hours  Variable overhead cost per machine-hour: $11.00$11.25\begin{array}{lrr}&\text { Actual } &\text { Budgeted }\\\text { Production } & 30,000 \text { units } & 24,000 \text { units } \\\text { Machine-hours } & 15,000 \text { hours } & 10,800 \text { hours } \\\text { Variable overhead cost per machine-hour: } & \$ 11.00 & \$ 11.25\end{array} -What is the variable overhead spending variance?


A) $3,750 favorable
B) $16,875 unfavorable
C) $13,125 unfavorable
D) $30,375 unfavorable

E) A) and D)
F) C) and D)

Correct Answer

verifed

verified

Compared to variable overhead costs planning,fixed overhead costs planning have an additional strategic issue of ________.


A) eliminating activities that do not add value
B) increasing the linearity between total costs and volume of production
C) choosing the appropriate level of investment
D) identifying essential value-adding activities

E) A) and C)
F) B) and D)

Correct Answer

verifed

verified

An unfavorable production-volume variance always infers that management made a bad planning decision regarding the plant capacity.

A) True
B) False

Correct Answer

verifed

verified

One possible reason for unfavorable variable overhead efficiency variance for materials handling is ________.


A) inefficient layout of product distribution channels
B) loosely budgeted standard hours
C) very low wait time at work centers
D) experienced but unmotivated employees

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The fixed overhead cost variance can be further subdivided into the ________.


A) price variance and the efficiency variance
B) spending variance and flexible-budget variance
C) production-volume variance and the efficiency variance
D) flexible-budget variance and the production-volume variance

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

Abby Company has just implemented a new cost accounting system that provides two variances for fixed manufacturing overhead.While the company's managers are familiar with the concept of spending variances,they are unclear as to how to interpret the production-volume overhead variances.Currently,the company has a production capacity of 54,000 units a month,although it generally produces only 46,000 units.However,in any given month the actual production is probably something other than 46,000. Required: a.Does the production-volume overhead variance measure the difference between the 54,000 and 46,000,or the difference between the 46,000 and the actual monthly production? Explain. b.What advice can you provide the managers that will help them interpret the production-volume overhead variances?

Correct Answer

verifed

verified

a.It is the difference between the 46,00...

View Answer

Radon Corporation manufactured 25,000 grooming kits for horses during March.The following fixed overhead data pertain to March:  Actual  Static Budget  Production 33,000 units 30,000 units  Machine-hours 6,100 hours 6,000 hours  Fixed overhead costs for March $153,000$144,000\begin{array}{lrr}&\text { Actual }&\text { Static Budget }\\\text { Production } & 33,000 \text { units } & 30,000 \text { units } \\\text { Machine-hours } & 6,100 \text { hours } & 6,000 \text { hours } \\\text { Fixed overhead costs for March } & \$ 153,000 & \$ 144,000\end{array} - What is the fixed overhead production-volume variance?


A) $9,000 unfavorable
B) $14,400 favorable
C) $14,400 unfavorable
D) $9,000 favorable

E) B) and C)
F) C) and D)

Correct Answer

verifed

verified

Which of the following statements is true of fixed overhead cost variances?


A) The difference between actual costs and flexible budget costs will give the production volume variance.
B) The difference between actual costs and static budget costs will give the production volume variance.
C) The difference between flexible budget costs and allocated overhead costs will give the production volume variance.
D) The difference between static budget costs and flexible budget costs will give the production volume variance.

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

Answer the following questions using the information below: Neocomfort Corporation manufactured 3,000 chairs during June. The following variable overhead data relates to June:  Budgeted variable overhead cost per unit $12.00 Actual variable manufacturing overhead cost $49,900 Flexible-budget amount for variable manufacturing overhead $47,800 Variable manufacturing overhead efficiency variance $720 unfavorable \begin{array}{ll}\text { Budgeted variable overhead cost per unit } & \$ 12.00 \\\text { Actual variable manufacturing overhead cost } & \$ 49,900 \\\text { Flexible-budget amount for variable manufacturing overhead } & \$ 47,800 \\\text { Variable manufacturing overhead efficiency variance } & \$ 720 \text { unfavorable }\end{array} -What is the variable overhead flexible-budget variance?


A) $2,100 favorable
B) $1,380 favorable
C) $2,100 unfavorable
D) $1,380 unfavorable

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

Under activity-based costing,the flexible-budget amount equals the static-budget amount for fixed overhead costs.

A) True
B) False

Correct Answer

verifed

verified

When fixed overhead spending variance is unfavorable,it can be safely assumed that ________.


A) flexible budget amount is higher than actual costs incurred
B) fixed overhead allocated for actual output is lower than actual costs incurred
C) flexible budget amount is lower than actual costs incurred
D) fixed overhead allocated for actual output is higher than actual costs incurred

E) None of the above
F) All of the above

Correct Answer

verifed

verified

Answer the following questions using the information below: Skizone Company's 4-Variance Analysis:  Production-Volume  Spending Variance  Efficiency Variance  Variance  Variable overhead $6,500 F$12,000U No variance  Fixed overhead  (a)   No variance $46,000U\begin{array} { | l | l | l | l | } \hline & & & \text { Production-Volume } \\ & \text { Spending Variance } & \text { Efficiency Variance } & \text { Variance } \\\hline \text { Variable overhead } & \$ 6,500 \mathrm {~F} & \$ 12,000 \mathrm { U } & \text { No variance } \\\hline \text { Fixed overhead } & \text { (a) } & \text { No variance } & \$ 46,000 \mathrm { U } \\\hline\end{array} -If Skizone's combined 4-Variance Analysis shows an unfavorable spending variance of $2,300,what is the fixed overhead spending variance (a) ?


A) $8,800 favorable
B) $4,200 unfavorable
C) $8,800 unfavorable
D) $4,200 favorable

E) A) and C)
F) B) and D)

Correct Answer

verifed

verified

Which of the following is the correct mathematical expression to calculate the fixed overhead production-volume variance?


A) static-budget amount − flexible-budget amount
B) flexible-budget amount − actual costs incurred
C) actual costs incurred − fixed overhead allocated for actual output
D) budgeted fixed overhead − fixed overhead allocated for actual output

E) All of the above
F) A) and C)

Correct Answer

verifed

verified

Use the below information to answer the following questions: Bekits Corporation manufactured 25,000 grooming kits for horses during March. The following fixed overhead data relates to March:  Actual  Static Budget  Production 37,500 units 36,000 units  Machine-hours 6,100 hours 5,940 hours  Fixed overhead costs for March $133,000$124,740\begin{array}{lrr}&\text { Actual }&\text { Static Budget }\\\text { Production } & 37,500 \text { units } & 36,000 \text { units } \\\text { Machine-hours } & 6,100 \text { hours } & 5,940 \text { hours } \\\text { Fixed overhead costs for March } & \$ 133,000 & \$ 124,740\end{array} -What is the amount of fixed overhead allocated to production?


A) $134,375.50
B) $124,740.00
C) $133,000.00
D) $129,937.50

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

The variable overhead flexible-budget variance can be further subdivided into the ________.


A) price variance and the efficiency variance
B) static-budget variance and sales-volume variance
C) spending variance and the efficiency variance
D) sales-volume variance and the spending variance

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

What are the two components of sales-volume variance? Explain why sales-volume variance could be helpful to managers.

Correct Answer

verifed

verified

The sales-volume variance is comprised o...

View Answer

Effective planning of variable overhead costs includes ________.


A) choosing the appropriate level of investment
B) eliminating value-added costs
C) redesigning products to use fewer resources
D) reorganizing management structure

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

Standard costing can provide managers with reliable and timely information on variable distribution overhead ________.


A) efficiency variances and production variances
B) production-volume variances and spending variances
C) efficiency variances and spending variances
D) production-volume variances and sales variances

E) B) and D)
F) C) and D)

Correct Answer

verifed

verified

Christine Corporation manufactures baseball uniforms and uses budgeted machine-hours to allocate variable manufacturing overhead.The following information pertains to the company's manufacturing overhead data:  Budgeted output units 10,000 units  Budgeted machine-hours 15,000 hours  Budgeted variable manufacturing overhead costs for 20,000 units $180,000 Actual output units produced 9,000 units  Actual machine-hours used 14,000 hours  Actual variable manufacturing overhead costs $171,000\begin{array}{lr}\text { Budgeted output units } & 10,000 \text { units } \\\text { Budgeted machine-hours } & 15,000 \text { hours } \\\text { Budgeted variable manufacturing overhead costs for } 20,000 \text { units } & \$ 180,000 \\& \\\text { Actual output units produced } & 9,000 \text { units } \\\text { Actual machine-hours used } & 14,000 \text { hours } \\\text { Actual variable manufacturing overhead costs } & \$ 171,000\end{array} What is the budgeted variable overhead cost rate per output unit?


A) $12.00
B) $12.21
C) $18.00
D) $19.00

E) A) and D)
F) None of the above

Correct Answer

verifed

verified

What is a standard costing system?

Correct Answer

verifed

verified

Standard costing is a costing system tha...

View Answer

Showing 101 - 120 of 176

Related Exams

Show Answer