In job shop (make-to-order) operations,the master production schedule is usually expressed in


A) end items.
B) modules.
C) kits.
D) customer orders.
E) warehouse orders.

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

MRP is an excellent tool for scheduling products with variable lead times.

A) True
B) False

Correct Answer

verifed

verified

Which portion of the master production schedule is normally fixed,frozen,or firm?


A) the entire schedule
B) only the aggregate schedule
C) only the middle of the schedule
D) only the near-term portion
E) only the far-term portion

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

Which of the following is false concerning enterprise resource planning (ERP) ?


A) It attempts to automate and integrate the majority of business processes.
B) It shares common data and practices across the enterprise.
C) It is inexpensive to implement.
D) It provides and accesses information in a real-time environment.
E) It requires an ongoing implementation process.

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

Consider the following bill of material.Forty units of Product A are needed.Assuming no on-hand inventory,and no scheduled receipts,explode the bill of material. Consider the following bill of material.Forty units of Product A are needed.Assuming no on-hand inventory,and no scheduled receipts,explode the bill of material.

Correct Answer

verifed

verified

Item A: 40 units;Item B: 40 ∗ ...

View Answer

Which of the following regarding enterprise resource planning (ERP) is true?


A) It involves an ongoing process for implementation.
B) It can incorporate improved,reengineered "best processes."
C) It has a software database that is off-the-shelf coding.
D) ERP systems usually include MRP,financial and human resource information.
E) All of the above are true.

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

The MPS calls for 110 units of Product A.There are currently 60 of Product A on hand.Each A requires 2 of Part B.There are 30 units of B available. a.Calculate the net requirements for A. b.Calculate the gross requirements for B. c.Calculate the net requirements for B.

Correct Answer

verifed

verified

(a)110 - 60 = 50; (b...

View Answer

Given the following bill of material Given the following bill of material   If the demand for product A is 50 units,what will be the gross requirement for component E? A) 4 B) 100 C) 200 D) 250 E) 300 If the demand for product A is 50 units,what will be the gross requirement for component E?


A) 4
B) 100
C) 200
D) 250
E) 300

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

The aggregate plan gets input or feedback from which of the following areas?


A) engineering
B) finance,marketing,and human resources
C) the master production schedule
D) procurement,production,and general management
E) all of the above

F) C) and D)
G) B) and D)

Correct Answer

verifed

verified

If safety stock is desired it should be built into which portion of MRP?


A) any
B) none
C) raw materials
D) finished assemblies
E) either raw materials or finished assemblies

F) B) and D)
G) A) and D)

Correct Answer

verifed

verified

What is DRP?

Correct Answer

verifed

verified

DRP is a time-phased...

View Answer

A(n)________ system is packaged business software that automates and integrates the majority of their business processes,shares common data and practices across the entire enterprise,and produces and accesses information in a real-time environment.

Correct Answer

verifed

verified

enterprise...

View Answer

What are the advantages of enterprise resource planning (ERP)?

Correct Answer

verifed

verified

ERP provides integration of the supply c...

View Answer

If parts and subassemblies common to a variety of products are managed through the supermarket concept,formal order releases for such parts are not necessary.

A) True
B) False

Correct Answer

verifed

verified

Describe finite capacity scheduling.How is it more realistic than MRP?

Correct Answer

verifed

verified

FCS provides the precise scheduling need...

View Answer

A manufacturing company is trying to determine the cost of materials used to produce an A.If Fs cost $1 and Ds cost $2 how much does it cost to produce an A (in F and D materials only)?

Correct Answer

verifed

verified

blured image Using an explosion shows that...

View Answer

Describe briefly the information requirements of basic and extended MRP systems.Comment on the challenge of maintaining timely,accurate information for a large manufacturing operation based on MRP.

Correct Answer

verifed

verified

MRP requires very high accuracy of inven...

View Answer

The following table is an example of a(n) The following table is an example of a(n)    A) aggregate plan. B) load report. C) master production schedule. D) capacity plan. E) inventory record.


A) aggregate plan.
B) load report.
C) master production schedule.
D) capacity plan.
E) inventory record.

F) A) and C)
G) B) and D)

Correct Answer

verifed

verified

If 100 units of Q are needed and 10 are already in stock,then the gross requirement is 100 and the net requirement is 90.

A) True
B) False

Correct Answer

verifed

verified

Each X requires 2 of component Y;each Y requires 4 of part Z.The lead time for assembly of X is 1 week.The lead time for the manufacture of Y is 1 week.The lead time for the procurement of Z is 6 weeks.The cumulative lead time for X is ________ weeks.


A) 6
B) 7
C) 8
D) 10
E) cannot be determined

F) C) and E)
G) A) and D)

Correct Answer

verifed